Planned
activities for the Week of January 16-20
á Southeast end of Horsetooth Reservoir
o Installation of bases and bottom sections of new
transmission poles using a small crane.
á Pineridge
o Excavation and concrete work for new pole foundations. Traffic control will be provided to avoid conflicts with trail use.